Client task
Quickly bring a new Belgrade Waterfront apartment to a true “move‑in ready” condition: add partitions for the required layout, level and paint the walls, fully refurbish the kitchen and two bathrooms, and upgrade the electrical system for new equipment.
Constraints and risks
Tight project timeline
Careful work required in a new finished space without damaging existing surfaces
What was done
Layout: installation of additional partitions for the new floor plan.
Finishes: Q3 wall levelling, wall and ceiling painting, lacquered engineered wood flooring, porcelain tile installation.
Kitchen and bathrooms: full renovation and complete replacement of plumbing fixtures.
Engineering and fit‑out: electrical upgrades, new lighting, switches and sockets, installation of CCTV, Wi‑Fi access points and furniture.